Pull the multi-party confirmations and multi-system data lookups of rush-order review into one process
For PMC and sales roles at manufacturing and industrial companies, for acceptance review of rush and non-standard orders. The problem it addresses: sales, engineering, procurement, production, and quality confirm back and forth, and staff still have to switch between ERP, MES, and APS to pull numbers — and even then may not answer accurately. The source marks the industry as Manufacturing.
First work with sales and PMC to fix the review's conclusions as fixed fields: can the order be accepted, earliest delivery date, which roles must sign. Only when the conclusion format is set do the later data pulls and human confirmations have a clear output.
List the must-read fields in three classes — ERP orders and inventory, MES work in process, APS scheduling — into one data-pull checklist; fields that cannot be read yet get manual backfill first, and never assume the systems already sync automatically.
For each confirmation step — engineering, procurement, quality, production — spell out: who answers, answers what, within how long, and who to escalate to when the time is exceeded. Without this table grounded, the cross-department relay jams at the waiting-for-people step.
Replay rush orders that already happened, compare the process's conclusions against the actual outcomes order by order, note where they diverge, and then revise the rules; going live without a replay means trial-and-error on real orders.
Add one fixed column to the review conclusion: which in-production orders this acceptance would crowd out or delay. If you only answer whether the order can be accepted, PMC still has to redo the schedule after receiving the conclusion.