Solution #0144 · All industries · General

Delivery Chase Log and Daily Chase List

Log every delivery chase in a ledger, and see on one page who to chase today

Score
10
Internal scoring scale
Roles
Procurement
Frontline role
Industry
All industries
General
Maturity
Live
Validated in practice
01 — Business fit

Who should use it, and when

Who should use it: procurement staff who chase delivery dates across multiple suppliers — especially those running several orders at once and chasing from memory and chat history. What it solves: the chase leaves no trail, so afterward no one can say who promised what, or when. The source lists only the role, Procurement, and leaves the industry unmarked.

02 — Key steps

The key moves that make it work

1
Fix the ledger fields first

Fix these columns: order number, supplier, promised delivery date, last chase date, their reply, and next follow-up date. Set the fields before you start filling anything in — retrofit them later and you will be able to find nothing.

2
Log it right after every chase

The moment a call ends or a message goes out, add a row: time, contact person, and their exact words. Skip a day and the backfilled row is almost always wrong.

3
Filter the list every morning

Filter by next follow-up date to pull out the rows due today and the rows already overdue — that is the day's chase list. Chase overdue first, then due; do not order it by gut feel.

4
Keep proof at the key moments

For a critical delivery date, send the ledger entry by email or message and ask for a one-line confirmation. A reply puts both sides on record; if they stay silent, mark it unconfirmed in the ledger anyway.

5
Grade the overdue items first

Sort the rows into tiers: hits the production schedule, hits customer delivery, or only affects stock replenishment. Escalate only the first two tiers to the supervisor, so everything stops being marked urgent.

TAKEAWAY
The value is in logging the same day, in full
None of this creates new information; it writes down the chasing that is already happening. Whether it kills the 'why didn't you tell me sooner' argument depends on records being written the same day and written in full.
03 — Risks & pitfalls

What to know before you start

Risk 1 · Records turn into backfillsChase now, write later from memory, and both the times and the quoted words drift. When a real dispute shows up, this record is the thing that falls apart.
Risk 2 · The other side denies itThe ledger is written by procurement alone. Records the supplier never confirmed carry limited weight in a dispute. Without a reply at the key moments, both sides will keep telling their own story.
Risk 3 · The list only growsWith many orders, overdue rows pile up. Without tiering and a named owner per row, the list becomes something everyone glances at daily and nobody works.