Turn every fault work order into the energy not generated and the component responsible
Built for production and operations-and-maintenance roles at wind farms, and for whoever accounts for energy output and losses. The problem it solves: the work orders are all closed out, but no one can say how much energy the farm failed to generate that month, or which component caused the shortfall. The source marks the industry as Energy & Utilities and the role as production; it is a live, industry-specific solution with no measured results yet.
Write the method down in plain text: whether the baseline is the theoretical power curve or the same period in prior years, and whether curtailed hours count as losses. Decide all of this up front. If the method is not consistent, the numbers from individual work orders will never add up.
Map the fault descriptions in each work order to component and system codes, and fill in the missing codes first. If 137 work orders each describe faults their own way, the totals will not reconcile when you aggregate by component, and attribution stops at the single work order.
Work-order start and end times, turbine stoppages or derating, and wind-speed data all need to sit on the same timeline. For stretches with no sensor data or bad timestamps, mark them 'undeterminable' outright; do not estimate to fill the gap.
Each work order produces one line: energy lost, component responsible, calculation basis, and reviewer. Enter it into the table only after a human review, so that if anyone questions a number later, you can trace it back to the original basis.
Put each component's energy loss and work-order count in one sheet. Focus on components with few work orders but large losses; that list becomes next month's priority order for on-site inspection.