Solution #0600 · IT & Internet · Industry-specific

Implementation Log Archiving and Delay Attribution — 37 Days of Delay: 21 the Client's, 11 Change-Related, 5 Won Back

Helps delivery project managers split delay days by responsibility and pay less in penalties

Score
12
Internal scoring scale
Roles
Operations
Frontline role
Industry
IT & Internet
Industry-specific
Maturity
Live
Validated in practice
01 — Business fit

Who should use it, and when

For implementation and delivery projects in IT & Internet that charge delay penalties weekly — used by project managers, delivery operations, and contract administrators. The problem: when a project slips, nobody can say which days belong to whom, and your own side eats the whole penalty. The source lists the role as Operations and the industry as IT & Internet.

02 — Key steps

The key moves that make it work

1
Write daily, archive the same day

The implementation log records, per day, who was on site, what was completed, what blocked work, and who was being waited on — archived the same day with a timestamp. Backfilled records carry weak evidentiary weight; material assembled from memory rarely holds up in a dispute.

2
Client-caused stalls need written traces

Any stall waiting on a client reply, environment, or data goes to the client's contact the same day by email or meeting minutes, with a request to confirm in writing. One-way notices without a reply usually don't count those days against the client.

3
Number change orders separately

Each change order records when it was raised, when confirmed, and days of impact, numbered separately from the daily log. Days consumed by a change must trace back from the change order to specific log entries, or they get counted as your own delay.

4
Agree the responsibility categories first

Before kickoff, agree with the client on three buckets — client side, change, own side — and what evidence each requires. Without settled definitions, the split of delay days becomes two different stories, and the split is useless.

5
Build the ledger before talking to the client

Assemble a day-by-day delay ledger with a penalty estimate (per the contract clause of 0.5%-1% per week, capped at 10% of contract value), check internally that the evidence is complete, and only then take it to the client.

TAKEAWAY
Logs first, attribution second
The value isn't a pretty split — it's leaving a checkable record every day. When the record is incomplete, any attribution is just two sides with different stories.
03 — Risks & pitfalls

What to know before you start

Risk 1 · Backfilled logs don't hold upIf the log is written only after delays occur, timestamps and content won't line up and the client can deny them. The plan only works when the log is written as daily routine; starting at settlement stage is nearly useless.
Risk 2 · The client won't sign receiptsThe client contact may acknowledge verbally without written confirmation, or a new contact may not honor a predecessor's signature. Those days stay stuck in pending — computable in the ledger, uncollectable at the negotiating table.
Risk 3 · One day claimed twiceClient causes and changes often overlap, and one day can count as both client waiting and change impact. Without a single-owner rule, the two records contradict each other and weaken the whole claim.