Helps delivery project managers split delay days by responsibility and pay less in penalties
For implementation and delivery projects in IT & Internet that charge delay penalties weekly — used by project managers, delivery operations, and contract administrators. The problem: when a project slips, nobody can say which days belong to whom, and your own side eats the whole penalty. The source lists the role as Operations and the industry as IT & Internet.
The implementation log records, per day, who was on site, what was completed, what blocked work, and who was being waited on — archived the same day with a timestamp. Backfilled records carry weak evidentiary weight; material assembled from memory rarely holds up in a dispute.
Any stall waiting on a client reply, environment, or data goes to the client's contact the same day by email or meeting minutes, with a request to confirm in writing. One-way notices without a reply usually don't count those days against the client.
Each change order records when it was raised, when confirmed, and days of impact, numbered separately from the daily log. Days consumed by a change must trace back from the change order to specific log entries, or they get counted as your own delay.
Before kickoff, agree with the client on three buckets — client side, change, own side — and what evidence each requires. Without settled definitions, the split of delay days becomes two different stories, and the split is useless.
Assemble a day-by-day delay ledger with a penalty estimate (per the contract clause of 0.5%-1% per week, capped at 10% of contract value), check internally that the evidence is complete, and only then take it to the client.