Solution #0705 · IT & Internet · Industry-specific

AI Cooling-Plant Control Cuts Data Center PUE

For existing data halls: a way to tune the cooling plant without downtime, saving power and inspection labor

Score
8
Internal scoring scale
Roles
Operations
Frontline role
Industry
IT & Internet
Industry-specific
Maturity
Case-verified
Verified case
01 — Business fit

Who should use it, and when

A good fit for existing data centers that already have cooling plant equipment and basic monitoring, high rack density, and electricity as the largest operating cost — especially Tier-A/Class-A halls that cannot shut down for retrofit. The source lists the industry as IT & Internet; the subject is a Class-A third-party data center in South China with roughly 1,000 racks. The roles are data hall operations and infrastructure leads, and the problem is that every bit of PUE reduction is hard-won and tuning relies on human experience.

02 — Key steps

The key moves that make it work

1
Confirm data can be collected in full first

Points for chillers, pumps, cooling towers and end-state temperature/humidity must be brought in first; with one data stream missing, load prediction and optimization later have no basis. Check each point against the actual equipment before go-live — do not enter automatic regulation until this step is done.

2
AI for load prediction and optimization

The model predicts cooling load for the coming period, picks a more power-efficient combination from all available equipment, and sets the supply water temperature. People used to decide from experience how many chillers to run and what water temperature; now the model computes and people review.

3
Humans set the safety bounds first

Constraints like temperature/humidity limits, equipment start/stop counts and minimum standby units are written as rules by operations; AI only issues commands within them. Anything beyond the bounds reverts to human confirmation — better to skip one adjustment than touch the compliance red line.

4
An alarm center takes over routine inspection

Shift-based manual meter reading and walk-throughs are replaced by a unified alarm center watching for anomalies; people move from scheduled inspection to handling alarms and reviewing adjustment records. The prerequisite: alarm thresholds set per device on site, otherwise false alarms pile up daily and nobody reads them.

5
Replicate without touching the chillers

The source's path is no downtime and no chiller retrofit — only adding the data acquisition and control layer. Following that idea, trial on one subsystem of the cooling plant first, confirm regulation does not affect temperature/humidity compliance, then extend to the whole plant.

TAKEAWAY
Set the bounds first, then let the machine tune
What is worth learning is the division of labor: people write the safety bounds and compliance requirements clearly, AI then does load prediction and global optimization within them, and the headline numbers are reference, not promises.
03 — Risks & pitfalls

What to know before you start

Risk 1 · Applying it unchanged at a different scaleThe case is a Class-A hall with roughly 1,000 racks; equipment models, redundancy and load curves are not disclosed. Halls that differ greatly in rack count and cooling-load characteristics gain no reference value from reusing the same parameters and rules.
Risk 2 · Safety bounds set too looseWidening temperature/humidity allowances or permitting frequent start/stops to save more power lowers consumption short-term but can pull the hall out of compliance and accelerate wear. Bounds must be set by operations per site codes, with review records kept.
Risk 3 · Treating the result as your expectation1.38 to 1.34 is this project's vendor-reported, media-disclosed result — a single sample. Adopting it as your own hall's target invites a mismatch at acceptance; measure a baseline before setting targets.
04 — Results & evidence

What the results look like

Case: A Class-A third-party data center in South China (Mushroom IoT client, anonymized at client request; organization name not publicly disclosed) (2026) · vendor-reported

Measured impactPUE fell from 1.38 to 1.34, saving about 700,000 kWh per year, an energy-savings rate of about 10% (vendor-reported, disclosed by media in 2026)

Vendor-reported, single-project sample; measurement method and statistics period not stated — cite with attribution.

Source: https://developer.cloud.tencent.com/article/2759987?policyId=1004